Status Report for Firefox on iOS for the period of 09/09/2015 - 16/09/2015
Overall Project Health
| This Week
|
Last Week
|
|

|

|
Exec Summary/Hot Topics
- V1.0 has now been made available in Canada.
- V1.1 estimation of initial scope breakdown was completed, but still some additional clarification/breakdown trickling in.
- Schedule for V1.1 available (see mana link at the end of this report)
- V1.1 Build#2 will be made available internally, and will also be the first build to release externally via TestFlight
- String freeze is THIS FRIDAY September 18th
- Scope is being monitored and managed aggressively. Any 'nice-to-have' features that do not have strings available for the 18th will be cut from the list.
- 'FxA Sign-up From Device' is considered 'At Risk'. Required resources are unavailable currently due to other priority work assignments.
Risks & Issues
| Description of Risk/Issue
|
State
|
Owner
|
Plan to Resolve/Mitigation
|
Target Date
|
| Resourcing constraints
|
OPEN - Monitor
|
Jenn/Eng Mgt
|
The team is smaller by 1.5 full-time, plus 1 intern, compared to V1.0 resourcing over the past few months. Scope and resource allocation must be monitored closely. Currently affecting feature development for 'FxA Sign-Up From Device'.
|
Ongoing
|
| Timeline constraints
|
OPEN - Monitor
|
Jenn/Eng Mgt
|
Submission target is mid-October to align with campaign target dates, leaving litle development time, to deliver must-have features. No scope creep can be permitted, and progress to be monitored closely.
|
Ongoing
|
|
|
|
|
|
|
|
|
|
|
|
|
Accomplished for the Last Period
- V1 launched in Canada
- Breakdown of V1.1 must-have requirements, and sizing of breakdown outputs
- V1.0.1 build released to test flight. Will be used as our interim bug-fix release, which is the last until V1.1.
- First V1.1 build released to internal aurora
- V1.1 milestone schedule defined and committed to by the team
- Team continues working toward V1.1 features, particularly focusing on finalizing strings
Planned for Last Period but Not Accomplished
Planned for the Upcoming Period
- String Freeze 9/18
- V1.1 Build #2 planned for 9/17
- Feature development continues
Status Details
Important Links/References