Program Management/Weekly-Status-Reports/2013-04-23

From New wiki
Jump to navigation Jump to search

Agenda

  • FFOS Madrid work week recap
  • Enhancements to FFOS burndowns
  • Onboarding for new FFOS PM - Candice

Dietrich

Erin

Lawrence

Martin

Michael

  • MMS Work week set up
  • Revise LGE v1.1 Gantt
  • Milestones for intermediate deliverables and how to show them

Marco

Metro Highlights

  • Team completed 75 story points across 25 features at the conclusion of Iteration #5 - a 19% increase in performance from the previous iteration.
  • Team has established a new average velocity rate of 47 story points per iteration at the conclusion of Iteration #5 - a 17% increase in performance from the previous iteration.
  • Overall performance gain in story points and velocity at the conclusion of Iteration #5 has resulted in a new production forecast release of December 23, 2013 - a reduction of 3 iterations from the previous release update.
  • Product Manager review of V1 Release List resulted in the removal of 9 Feature Stories to V2.
  • At the conclusion of Iteration #6 the project will have acquired enough data to present three release forecast scenarios: Worst, Expected and Best case.

Iteration Performance Summary

  • Total Work: 109 total story points - 27 bugs.
    • 16 feature stories.
    • 9 defect stories.
    • 2 change stories.

  • Completed Work: 27 story points closed - 15 bugs - 24% complete.
    • 7 feature stories.
    • 7 defect stories.
    • 1 change story.

  • Remaining Work: 82 story points closed - 12 bugs - 76% complete.
    • 9 feature stories.
    • 2 defect stories.
    • 1 change story.

Iteration Work Details

<bugzilla>

   {
       "id": "831916, 831918, 831934, 833133, 833182, 835623, 838497, 849395, 850737, 851900, 852090, 855578, 862054, 831894, 831919, 833130, 833131, 833132, 833200, 852805, 854070, 854077, 855581, 855587, 859447, 860994, 862025, 863060"
   }

</bugzilla>

Sheila

  • FFOS
    • Fully sucked into the FFOS work to help ship 1.0.1 and 1.1
    • Helping team move to more agile model for future releases
    • Onboarding plan for new PM starting May 13th
    • Working with other PMSs (ie: Marketplace, Marketing on higher level status for FFOS program)
  • FHR
    • What's next - looking at Fx23
    • Tracking final pieces for Fx21
  • Reviewing revised use cases and requirements for Product Requirements Management System