Websites/WebifyMe/Meeting Apr 13

From New wiki
Jump to navigation Jump to search

Webifyme Checkin Apr 13th

Timelines

We're in the home stretch... scope is fixed and TBG is almost code complete.

Critical Path Timeline

Apr 15th - TBG Staging bugs Fixed

Apr 22nd (1 week approx, 2 weeks would be Apr 29th worse case) Webifyme.allizom.org staged

Apr 25th - WebQA starts

May 6th - WebQA finishes

May 9th - Go / No Go Decision

May 10th - Prod launch

Note

Any slippage in critical path slips prod launch date

Any unaddressed blocker bugs will slip Go / No Go decision

In Parallel Timeline

Apr 24 - May 6th - Infrasec testing (4 days approx)

Apr 22nd - May 6th - Operations builds out prod environment (1 week approx)

Apr 18th - May 6th - L10n Estimate TBD (Apr 15th string freeze)

Triage as needed - TBG, Grace, Krupa, ozten

Apr 15th - May 6th - TBG fixing bugs which have been reported

Operations Notes:

  • 2 weeks of work all together (medium risk estimate)
  • We'll put app on the Engagement cluster

WebQA

  • Estimated 10 days to test
  • Asked about Supported browsers
  • Will put 15-20 external testers on project
  • Load testing? - Not needed unless peak usage estimates are large
  • Accessibility - (optional :| ) Marco Zehe and others to test
  • NoJS - Need string before string freeze

L10n

  • Estimate TBD
  • 10 locales?
  • Already know about project and some bugs have been filed

InfraSec

  • Estimate 4 days
  • Once everything works (after WebQA pass starts)

TBG

  • Tiffany, Dawn from TBG to join weekly meetings

Next Actions

Grace

[] Stas or Gandalf - L10n time estimates, list of locales

[] Estimate peak and average traffic to the site

[] Estimate conversion rate for people finishing the quiz (image generated)

Stephen

[] Contact Accessibility community for testing

Ozten

[x] Resend https://wiki.mozilla.org/QA/Execution/Web_Testing/Project_Checklist to TBG

[x] Will send email to Gandalf and Stas to ask who will extract strings and setup SVN repo

Next Meeting

April 20th